Force Main and FRP Installations

4 de marzo de 2026

JF Wilkerson’s subcontractor has requested to work this Saturday, March 7, 2026, on the 24-inch force main installation near the end of West Middleton Drive, primarily in the area between Stardust Lane and West Middleton Drive, near nearby residences.

Click this link to view work zone: https://static.wixstatic.com/media/568a25_c5a23414489e4637876f3d484bbb783d~mv2.png

CP#1 Update: Work will continue this week at the pump station site, including backfilling and hauling fill material to support activity along the East Middleton corridor. Crews will also continue roofing work, and pipeline installation will remain underway—placing new force main pipe from the East Middleton Lift Station area and installing additional large-diameter pipe near Stardust Lane.

CP#2 Update: Crews will continue installing FRP sewer main segments. Drilling activity remains paused at this time while an Enbridge Gas coordination issue is resolved.